dc.description.abstract | Lean is common sense and good business sense. As organizations grow and become more
successful, they begin to lose insight into the basic truths of what made them successful.
Organizations have to deal with more and more issues that may not have anything to do with
directly providing products or services to their customers. Lean is a holistic management
approach that brings the focus of the organization back to providing value to the customer.
In August 2002, Mrs. Darleen Druyun, the Principal Deputy to the Assistant Secretary of the Air
Force for Acquisition and government co-chairperson of the Lean Aerospace Initiative (LAI),
decided it was time for Air Force acquisitions to embrace the concepts of lean. At her request,
the LAI Executive Board developed a concept and methodology to employ lean into the Air
Force’s acquisition culture and processes. This was the birth of the “Lean Now” initiative. An
enterprise-wide approach was used, involving Air Force System Program Offices (SPOs),
aerospace industry, and several Department of Defense agencies. The aim of Lean Now was to
focus on the process interfaces between these “enterprise” stakeholders to eliminate barriers that
impede progress. Any best practices developed would be institutionalized throughout the Air
Force and the Department of Defense (DoD).
The industry members of LAI agreed to help accelerate the government-industry transformation
by donating lean Subject Matter Experts (SMEs) to
mentor, train, and facilitate the lean events of
each enterprise. Currently, the industry SMEs and the Massachusetts Institute of Technology are
working together to help the Air Force develop its own lean infrastructure of training courses and
Air Force lean SMEs.
The first Lean Now programs were the F/A-22, Global Hawk, and F-16. Each program focused
on specific acquisition processes. The F/A-22 focused on the Test and Evaluation process; the
Global Hawk focused on Evolutionary Acquisitions; and the F-16 focused on improving the
Contract Closeout process.
Through lean, each enterprise made many significant improvements. The F/A-22 was able to
reduce its Operational Flight Plan (OFP) Preparation and Load process time of 2 to 3 months
down to 7 hours. The Global Hawk developed a new production plan that increases the annual
production of its Integrated Sensor Suite from 3 per year to 6 per year. The F-16 enterprise
generated and is working 12 initiatives that could result in a contract closeout cycle time
reduction of 3 to 7 years. Each enterprise continues to generate more lean initiatives that focus
on other areas and processes within their respective enterprises. | en |