| dc.contributor.author | Matthews, Lynn D. | |
| dc.contributor.author | Crew, G. B. | |
| dc.date.accessioned | 2026-03-05T19:11:53Z | |
| dc.date.available | 2026-03-05T19:11:53Z | |
| dc.date.issued | 2015-03-29 | |
| dc.identifier.uri | https://hdl.handle.net/1721.1/165051 | |
| dc.description | This report was prepared to report on APP commissioning progress, provided as ALMA Technical Note #16. | |
| dc.description.abstract | The first Commissioning and Science Verification (CSV) mission for the ALMA Phasing Project (APP) took place during the ALMA EOC Week from 2015 January 6-13. The formal commencement of APP CSV activities followed the provisional acceptance of the APP hardware during a formal review by JAO that took place on 2014 December 11. This is a report of activities during the week. | en_US |
| dc.description.sponsorship | The NA ALMA Development Program | en_US |
| dc.publisher | The Joint ALMA Observatory | en_US |
| dc.subject | Radio Astronomy | en_US |
| dc.subject | ALMA Observatory | en_US |
| dc.subject | Very Long Baseline Interferometry | en_US |
| dc.title | Summary of the First ALMA Phasing Project (APP) Commissioning and Science Verification Mission: 2015 January 6-13 | en_US |
| dc.type | Technical Report | en_US |
| dc.identifier.citation | https://almascience.nrao.edu/documents-and-tools/alma-technical-notes/ALMATechnicalNotes16_FINAL.pdf | en_US |